Rt. 79 Pump Station and Force Main Reconstruction

Carbro performed reconstruction of the Route 79 Pump Station and replacement of approximately 7,655 LF 8″-18″ force main along Route 79. Carbro’s work included the installation of new pumps, controls, electrical equipment, grinders, a precast concrete building, precast concrete structures, a generator, piping, valves, micro-piling, and restoration.

Client
Western Monmouth Utilities Authority
Value
$6,378,652


OtherProjects

JCMUA East Side and West Side Emergency Generators

Previous Project

Green Brook Flood Control Project Segment C2

Next Project