An Accelerated Bridge Construction (ABC) project constructed in five stages – the first two stages include work in the Route 3 median improving both bridges piers; drainage improvements; utility relocation; and upgrades at the Polito Avenue and Rutherford Avenue intersections, including traffic signal improvements and ADA compliant sidewalk ramps. Stage 3 is the reconstruction of the Ridge Road Bridge over Route 3, Stage 4 is the reconstruction of the Orient Way Bridge over Route 3, and Stage 5 will remove the existing bridge abutments from both bridges and provide a continuous full width right shoulder on Route 3 in both directions.

Client
NJDOT
Value
$26,702,582